McDermott Advances Scarborough EPCIC with Successful FPU Floatover
HOUSTON, May 13, 2025 /PRNewswire/ -- McDermott announces the safe, successful completion of fabrication, construction, and offshore floatover of the Scarborough floating production unit (FPU) topside and hull structures for Woodside Energy.
The contract, awarded in 2021, followed the successful delivery of front-end engineering design for the Scarborough Energy Project's FPU and includes engineering, procurement, construction, installation and commissioning (EPCIC) services. McDermott is delivering design, fabrication, integration, transportation and installation of an approximately 30,000-metric-ton topside and 37,000-metric-ton hull structure, making it the largest floating production facility the company has ever designed and built, and one of the largest semi-submersible production platforms built in offshore history.
Topsides fabrication was completed at McDermott's joint venture yard, Qingdao McDermott Wuchuan (QMW), in Qingdao, China, while the hull was constructed by COSCO in its Qidong shipyard, also in China. The topsides have six deck levels; 169 core equipment units, including three gas turbine-driven export gas compressors and three main generators with waste heat recovery systems; more than 50,000 meters of piping; one million meters of cabling; 568 integrated subsystems and a battery energy storage system, supporting operational emissions reduction.
Earlier this month, both structures were transported offshore, and the topsides installed onto the hull via floatover off the coast of Dalian, China.
Following the successful floatover, the FPU arrived at CIMC's Raffles yard in Yantai, China, for final integration works. From there, it is expected to sail away to Western Australia, where it will be moored at the Scarborough gas field approximately 375 kilometers offshore from the Burrup Peninsula.
About McDermott
McDermott is a premier, fully-integrated provider of engineering and construction solutions to the energy industry. Our customers trust our technology-driven approach engineered to responsibly harness and transform global energy resources into the products the world needs. From concept to commissioning, McDermott's innovative expertise and capabilities advance the next generation of global energy infrastructure—empowering a brighter, more sustainable future for us all. Operating in over 54 countries, McDermott's locally-focused and globally-integrated resources include more than 30,000 employees, a diversified fleet of specialty marine construction vessels and fabrication facilities around the world. To learn more, visit www.mcdermott.com.
Forward-Looking Statements
McDermott cautions that statements in this communication which are forward-looking, and provide other than historical information, involve risks, contingencies and uncertainties. These forward-looking statements include, among other things, statements about the expected scope and execution of the project discussed in this press release. Although we believe that the expectations reflected in those forward-looking statements are reasonable, we can give no assurance that those expectations will prove to have been correct. Those statements are made by using various underlying assumptions and are subject to numerous risks, contingencies and uncertainties, including, among others: adverse changes in the markets in which we operate or credit or capital markets; our inability to successfully execute on contracts in backlog; changes in project design or schedules; the availability of qualified personnel; changes in the terms, scope or timing of contracts, contract cancellations, change orders and other modifications and actions by our customers and other business counterparties; changes in industry norms; actions by lenders, other creditors, customers and other business counterparties of McDermott and adverse outcomes in legal or other dispute resolution proceedings. If one or more of these risks materialize, or if underlying assumptions prove incorrect, actual results may vary materially from those expected. You should not place undue reliance on forward-looking statements. This communication reflects the views of McDermott's management as of the date hereof. Except to the extent required by applicable law, McDermott undertakes no obligation to update or revise any forward-looking statement.
Contacts:
Global Media Relations
Reba Reid
Senior Director, Global Communications and Marketing
+1 281 588 5636
RReid@McDermott.com
View original content to download multimedia:https://www.prnewswire.com/news-releases/mcdermott-advances-scarborough-epcic-with-successful-fpu-floatover-302454454.html
SOURCE McDermott International, Ltd